Role
Prime Contractor
ZGC managed the complete restoration program, specialty trades, scheduling, sequencing and handover.
Medical Facility Restoration | Dallas, Texas
Following a vehicle impact at an occupied Ottobock patient-care clinic in Dallas, ZGC served as prime contractor for commercial storefront repair, automatic sliding-door replacement, insulated glazing and adjacent interior wall restoration.
Role
ZGC managed the complete restoration program, specialty trades, scheduling, sequencing and handover.
Project Value
Documented billed project value for the storefront, entrance and interior restoration work.
Trade Management
ZGC coordinated four subcontractor companies across the multi-trade restoration program.
Closeout
Successful final walkthrough and handover with no punch-list deficiencies identified.
The Restoration Challenge
A vehicle impact damaged the commercial storefront, primary automatic entrance and adjacent interior wall construction at the Dallas clinic.
The repair required more than replacing broken glass. ZGC had to coordinate structural storefront framing, insulated safety glazing, a complete automatic sliding-door system and interior metal-stud/drywall restoration as one integrated project.
Scheduling also had to account for clinic operations and reliable ADA accessibility for patients while specialty materials and the automatic-door package moved through fabrication and delivery.
Project Profile
Storefront and Entrance Systems
The damaged entrance was rebuilt with coordinated storefront framing, insulated Low-E safety glazing and a complete automatic sliding-door package.
Two damaged storefront bays were rebuilt with clear-anodized aluminum framing and 1-inch insulated Low-E tempered glass with tint/film matched to the existing storefront.
A Horton S2000 belt-operator system with a four-panel bi-parting configuration restored the clinic's primary automatic entrance.
BEA IXIO sensors, fail-secure autolock, motion activation, breakaway egress hardware and final commissioning were integrated into the replacement system.
Critical-Path Coordination
The automatic-door package became the project's critical-path item when manufacturing and procurement delays affected the original schedule. ZGC tracked the fabrication status, escalated with production and procurement, and coordinated the glazing trade around the revised delivery date.
Once the package arrived locally, ZGC synchronized the automatic-door and storefront crews so removal, framing replacement, header and jamb installation, glazing, sensor setup, calibration and operational testing could proceed in sequence.
This coordination reduced the risk of leaving the clinic entrance partially reconstructed while waiting on one specialty trade to catch up to another.
Entrance Profile
Interior Restoration
The impact also damaged the interior wall system. ZGC coordinated the wall restoration as part of the same prime contract so the storefront and interior finishes could be handed back together.
Two damaged 3-5/8-inch metal studs were removed and replaced with associated anchoring and track adjustment.
Approximately 80 SF of 5/8-inch drywall on both sides of the wall was repaired and finished to Level 4.
Repaired surfaces were primed and painted with two finish coats, blended into the surrounding clinic finishes.
Project Delivery
ZGC managed four subcontractor companies through the vehicle-impact restoration, including the specialty storefront/glazing and automatic entrance scopes, while coordinating interior wall restoration and project supervision.
On installation day, the teams removed the damaged entrance and storefront components, rebuilt the affected framing, installed the new automatic-door package and glazing, and completed sensor calibration and safety adjustments before handover.
The project concluded with a successful final walkthrough and handover, with no punch-list deficiencies identified. The completed work demonstrates ZGC's ability as a Dallas-Fort Worth commercial general contractor to coordinate multi-trade restoration inside an occupied medical facility.
Key Results
Related Capabilities
Storefront, glazing, framing, drywall, door and damage-restoration scopes managed through one accountable contractor.
Renovation and modernization planned around active offices, clinics, retail and other operating commercial facilities.
Multi-trade commercial construction from preconstruction and procurement through field execution, punch and closeout.
Commercial Property-Damage Restoration
ZGC manages multi-trade commercial restoration scopes where specialty systems and occupied-facility constraints have to come together cleanly.