Technical Training Infrastructure | Irving, Texas

Schindler Technical Learning Center expansion and renovation

ZGC served as prime contractor for a large-scale expansion and commercial finish-out at Schindler Elevator Corporation's Dallas-area technical learning center in Irving, combining elevator test infrastructure with offices, interior construction, MEP systems, fire protection and life-safety work.

Role

Prime Contractor

ZGC managed the overall construction program, sequencing, subcontractors, coordination and closeout.

Trade Management

21 Subcontractors

Twenty-one separate specialty subcontractor companies were coordinated across design, testing, structural, MEP, finish and specialty scopes.

Scope Growth

4 Change Orders

The project expanded through four change orders as additional facility requirements were incorporated into the work.

Closeout

Clean Handover

Perfect punch and handover, with no punch-list discrepancies, warranty callbacks or post-completion corrective work.

The Engineering Challenge

Constructing a new hoistway pit beneath an existing standing hoistway

One of the project's most technically demanding scopes was the installation of a new elevator hoistway pit beneath an existing standing hoistway structure. The work required careful sequencing and coordination across geotechnical investigation, engineering, excavation, concrete, testing, steel and specialty construction disciplines.

The objective was not a conventional demolition-and-rebuild approach. ZGC coordinated the work necessary to create the new pit below the existing structure while maintaining the integrity and alignment of the hoistway above.

The pit work included excavation, structural concrete, embedded components, pit lighting and electrical requirements, along with the inspections and testing necessary to support the completed training installation.

Schindler technical learning center elevator training infrastructure project completed by Ziggys General Contracting in Irving Texas

Project Profile

  • Schindler Elevator Corporation
  • 6631 N. Belt Line Road, Suite 130, Irving, Texas
  • Technical learning and elevator testing facility
  • Prime contractor: Ziggys General Contracting LLC
  • Two approximately 8' x 10' elevator pits
  • Completion and final billing: June 2025

Facility Expansion

A second pit and additional test tower expanded Schindler's operating capability

After the existing-hoistway pit work, ZGC constructed a second hoistway pit and coordinated erection of an additional elevator test tower, expanding the facility's technical-training capacity and elevator prototype-testing capabilities.

Second Hoistway Pit

Excavation, structural concrete, embedded components, electrical and related pit systems were coordinated for the additional training hoistway.

New Test Tower

Custom structural steel fabrication, welding and erection were coordinated to create the additional elevator training and prototype-testing structure.

Catwalk and Access

A connecting catwalk and access system integrated the hoistway structures and supported the expanded technical learning environment.

Commercial Interior Renovation

Commercial finish-out and interior renovation paired with technical infrastructure

The construction program extended beyond the elevator training area and included office, classroom, ceiling, flooring, lighting, HVAC, electrical and specialty upgrades throughout the facility.

Offices and Interior Build-Out

New office additions, partition framing, drywall, door installations, painting, classroom modifications and associated finish work.

Ceilings and Lighting

ACT ceiling replacement and conversion to a 2x2 tile system, coordinated with LED lighting upgrades and revised interior layouts.

Flooring and Finishes

Carpet renovation, cove base, epoxy floor coating, drywall repairs, painting and finish restoration across renovated spaces.

HVAC and Mechanical

HVAC modifications and air-distribution changes were coordinated around the new offices, classrooms and revised facility configuration.

Electrical

Three-phase and single-phase power, transformer requirements, lighting, outlets and equipment connections supported the new training infrastructure and renovated interiors.

Industrial and Specialty Systems

Industrial mesh fencing, specialty doors, Big Ass Fan installation and related facility systems were integrated into the completed training environment.

Life-Safety Integration

Fire protection and alarm systems were coordinated with the new facility configuration

The renovation required fire sprinkler system modifications and testing as the interior layout and technical infrastructure changed. Sprinkler work included system preparation, relocation of affected heads and pressure testing.

Fire alarm and controls integration was also coordinated with the large industrial fan system and the new hoistway/test-tower infrastructure, bringing the specialty equipment into the facility's life-safety strategy.

This coordination required the electrical, fire-protection, controls and specialty-equipment scopes to be sequenced as part of the overall construction program rather than treated as isolated installations.

Life-Safety Scope

  • Fire sprinkler system modifications
  • Sprinkler-head relocation
  • System pressure testing
  • Fire alarm and controls coordination
  • Big Ass Fan life-safety integration
  • New hoistway/test-tower system integration

Subcontractor Management

Twenty-one specialty subcontractor companies coordinated under one prime contractor

The project required ZGC to coordinate separate specialty companies across testing, design, structural, building systems, finishes and technical installations.

Testing and Design

  • Geotechnical report / geotechnical testing
  • Concrete core testing
  • Engineering
  • Architecture

Structural and Site Work

  • Excavation
  • Concrete
  • Steel fabrication
  • Welding
  • Fencing

Building Systems and Finishes

  • Electrical
  • HVAC
  • Plumbing
  • Framing
  • Drywall
  • Painting
  • Flooring
  • Epoxy floor coating
  • Door installation
  • Big Ass Fan installation
  • Fire sprinkler systems
  • Fire alarm systems integration

Project Outcome

Expanded technical capability with a clean construction closeout

The completed work expanded Schindler's Dallas-area technical learning environment with additional elevator training and prototype-testing infrastructure while modernizing the surrounding offices, classrooms and building systems.

ZGC carried the project through final punch and handover with no punch-list discrepancies identified. No warranty callbacks or post-completion corrective work have been required.

The result demonstrates ZGC's ability as a Dallas-Fort Worth commercial general contractor to manage complex tenant finish-out, commercial renovation, engineering, structural, MEP and life-safety scopes under one prime-contract management structure.

Key Results

  • Existing hoistway upgraded with a newly constructed pit below the standing structure
  • Second hoistway pit constructed
  • Additional elevator test/training tower erected
  • Training and prototype-testing capacity increased
  • Interior office and classroom areas renovated
  • MEP and life-safety systems integrated with new construction
  • Perfect punch and successful handover
  • No warranty callbacks

Related Capabilities

Tenant finish-out, commercial renovation and general contracting capabilities demonstrated on this project

Technical and Commercial Construction

Planning a complex facility expansion, tenant improvement or specialty construction project?

ZGC manages multi-trade commercial construction from preconstruction and engineering coordination through field execution, punch and closeout.